History | Structure | Tenders | projects | Circulars | Photo Gallery | Maps  
Click HereAnnexure

Projects Undertaken By HSRDC

In addition to management of funds of PWD (B&R) for various schemes such as LADT (Rural), LADT (Urban), deposit works, funds of Education Department, funds of Health Deptt. etc., the Corporation is taking up the following works:

  1.  Construction of various buildings in BPS Mahila Vishwavidhalaya at Khanpur Kalan (Sonepat) costing Rs. 103.36 crores – The project has been completed except hostels/guest houses.  The progress is as under:

·         Construction of Teaching block (Group–I) at B.P.S. Mahila Vishwavidhyala at Khanpur Kalan (Sonepat) costing Rs. 13.75 crores – Progress : Completed.

·         Construction of Teaching block (Group–II) at B.P.S. Mahila Vishwavidhyala at Khanpur Kalan (Sonepat) costing Rs. 13.75 crores – Progress : Completed.

·         Construction of Girls Hostel (Group-I) at B.P.S. Mahila Vishwavidhyala at Khanpur Kalan (Sonepat) costing Rs. 9.31 crores – Progress : 90% completed, Likely date of completion : 31.3.09

·         Construction of Girls Hostel (Group-II) at B.P.S. Mahila Vishwavidhyala at Khanpur Kalan (Sonepat) costing Rs. 9.31 crores – Progress : 95% Completed, Likely date of completion : 28.2.09

·         Construction of Girls Hostel (Group-III) at B.P.S. Mahila Vishwavidhyala at Khanpur Kalan (Sonepat) costing Rs. 9.31 crores – Progress : 95% Completed, Likely date of completion : 28.2.09

·         Construction of Guest House at B.P.S. Mahila Vishwavidhyala at Khanpur Kalan (Sonepat) costing Rs. 3.46 crores – Progress : 94% Completed, Likely date of completion : 20.2.09

·         Construction of Campus School at B.P.S. Mahila Vishwavidhyala at Khanpur Kalan (Sonepat) costing Rs. 4.37 crores – Progress : Completed

·         Construction of One house of Vice Chancellor residence (2775 SFT) & 15 houses of 1882 SFT at B.P.S. Mahila Vishwavidhyala at Khanpur Kalan (Sonepat) costing Rs. 3.46 crores – Progress : 99% Completed, Likely date of completion: 20.2.09

·         Construction of 32 houses of 1220 SFT at B.P.S. Mahila Vishwavidhyala at Khanpur Kalan (Sonepat) costing Rs. 3.63 crores – Progress : Completed

·         Construction of 48 houses of 600 SFT at B.P.S. Mahila Vishwavidhyala at Khanpur Kalan (Sonepat) costing Rs. 3.24 crores – Progress : Completed

·         Construction of internal roads in the campus of B.P.S. Mahila Vishwavidhyala at Khanpur Kalan (Sonepat) costing Rs. 6.48 crores – Progress : 90% Completed, Likely date of completion: 28.2.09

·         Construction of 11Kv Electrical Sub-stations and connections in various buildings in BPS Mahila Vishwavidhalaya, Khanpur Kalan (Sonepat) costing Rs. 4.53 crores – Progress : Collection of H.T. & L.T. cables, transformers, V.C.Bs. and construction of sub stations buildings completed, Likely date of completion : 28.2.09

·         Purchase of furniture for various departments in the BPS Mahila Vishwavidhalaya, Khanpur Kalan (Sonepat) costing Rs. 8.13 crores – Progress : 98% Completed, Likely date of completion : 15.2.09

·         Construction of boundary wall around newly acquired land in the BPS Mahila Vishwavidyalaya, Khanpur Kalan (Sonepat) costing Rs. 3.95 crores – Progress : 40%,  Target date : 30.06.09

  1. Construction of colony in Deenbandhu Chhotu Ram Thermal Power Project (DCRTPP) at Yamuna Nagar costing Rs. 50.15 crores – The project is likely to be completed by 30.6.09

·         Construction of CISF at Deenbandhu Chhotu Ram Thermal Power Project at Yamuna Nagar costing Rs. 3.52 crores – Progress : 98% Completed, Likely date of completion : 28.2.09

·         Construction of OHSR at  Deenbandhu Chhottu Ram Thermal Power Project at Yamuna Nagar costing Rs. 0.23 crores – Progress : Completed,

·         Construction of internal roads in  Deenbandhu Chhottu Ram Thermal Power Project at Yamuna Nagar costing Rs. 4.30 crores – Progress : 70% Completed, Likely date of completion : 31.3.09

·         Providing Water Supply, Sewerage & Water Drainage System in Deenbandhu Chhottu Ram Thermal Power Project at Yamuna Nagar costing Rs. 0.90 crores – Progress : 97% Completed, Likely date of completion : 28.2.09

·         Construction of Non Residential Buildings in Deenbandhu Chhottu Ram Thermal Power Project at Yamuna Nagar

·         Various Buildings (7 nos) costing Rs. 5.43 crores – Progress : 35% Completed, Target date : 30.4.09

·         Shopping complex, Dispensary, Bank, Post Office and Maintenance Office

(4 nos) costing Rs. 2.00 crores – Progress : 55% Completed, Target date : 30.4.09

·         Construction of Electrical sub station at Deen Bandhu Chhotu Ram Thermal Power Project at Yamuna Nagar costing Rs. 0.44 crores – Progress : 60% Completed, Target date : 31.3.09

·         Prov of 11 KV sub station including Electric Supply to buildings and street lights in DCRTPP colony costing Rs. 4.20 crores – Progress : 50% Completed, Target date : 25.3.09

·         Construction of Sewerage Treatment plant in the colony of Deenbandhu Chhotu Ram Thermal Power Project at Yamuna Nagar costing Rs. 0.39 crores – Progress : 99% Completed, Likely date of completion : 15.2.09

  1. Improvement of Gurgaon – Nuh – Rajasthan Border (SH-13) km 7.200 to 95.890 by four lanning, widening, strengthening, providing drains, widening of bridges and culverts, retaining structures and other miscellaneous works etc. (Amount Rs. 347.97 crores) – The project is likely to be completed by 10.06.2010. - Progress – 1%.  The Committee of Chief Engineer (Roads) and Chief Engineer (NCR) was constituted by the Government for deciding the issues of reconstruction / re-modeling of bridges, construction of diversion of bridges, reconstruction of roads, four-laning of some stretches of the roads etc. The Project has been inspected by the Committee and variations from DPR on the basis of site conditions have been approved.  The changes have been displayed on HSRDC’s website. Cost as per Agreement – Rs. 338.07 crores,  Cost as per revised Scope – No change.
  2. Improvement of Murthal-Sonepat-Sampla-Jhajjar-Dadri road (Section of SH-20) from RD 0.00 to 95.150 and Gurgaon- Farrukhnagar- Jhajjar road (SH-15A) from RD 5.500 to 46.250 by widening, strengthening, re-construction/raising, providing drains, widening of bridges and culverts, retaining structures and other misc. works etc. (amount Rs. 231.78 crores) – The project is likely to be completed by 03.12.2009.- Progress – 15%. The Committee of Chief Engineer (Roads) and Chief Engineer (NCR) was constituted by the Government for deciding the issues of reconstruction / re-modeling of bridges, construction of diversion of bridges, reconstruction of roads, four-laning of some stretches of the roads etc. The Project has been inspected by the Committee and variations from DPR on the basis of site conditions have been approved.  The changes have been displayed on HSRDC’s website. Cost as per Agreement – Rs. 240.45 crores,  Cost as per revised Scope – 248 crores. The major change in cost is due to CC pavement at Chhuchhakwas Chhara, reconstruction/raising in Sampla Jhajjar Section
  3. Widening and upgradation of Rai Nahra Bahadurgarh road (MDR-138) Km. 0.00 to 37.40 & Rohtak-Kharkhoda Delhi Border (SH-18) (Km.10.200 to 40.760) – (Amount Rs. 139.07 crores) – The project is likely to be completed by 03.12.2009. - Progress – 19%.  The Committee of Chief Engineer (Roads) and Chief Engineer (NCR) was constituted by the Government for deciding the issues of reconstruction / re-modeling of bridges, construction of diversion of bridges, reconstruction of roads, four-laning of some stretches of the roads etc. The Project has been inspected by the Committee and variations from DPR on the basis of site conditions have been approved.  The changes have been displayed on HSRDC’s website. Cost as per Agreement – Rs. 142.62 crores, Cost as per revised Scope – 148 crores. The major change in cost is due to raising/ reconstruction in Bahadurgarh.
  4. Improvement of Hodal – Nuh – Pataudi road (MDR-132) km 0.00 to 96.775 by reconstruction, widening, strengthening,  raising, providing drains, widening of bridges and culverts, retaining structures and other miscellaneous works etc. (Amount Rs. 239.87 crores) – The project is likely to be completed by 10.03.2010. - Progress – 5.  The Committee of Chief Engineer (Roads) and Chief Engineer (NCR) was constituted by the Government for deciding the issues of reconstruction / re-modeling of bridges, construction of diversion of bridges, reconstruction of roads, four-laning of some stretches of the roads etc. The Project has been inspected by the Committee and variations from DPR on the basis of site conditions have been approved.  The changes have been displayed on HSRDC’s website. Cost as per Agreement – Rs. 239.80 crores,  Cost as per revised Scope – 244.48 crores. The major change in cost is due to raising/ reconstruction in Nuh Palwal Section & four laning at Tauru & Pataudi.
  5. Construction of colony in Rajiv Gandhi Thermal Power Plant, Khedar(Hisar) (Amount Rs. 70.00 crores) – The project is likely to be completed by 31.03.2010.:

·         Construction of 144 nos type V and 24 nos type VI houses in the campus of RGTPP at Khedar in Hisar district costing Rs. 37.37 crores – Progress : 16% achieved against 22%, Target date : 11.3.10

·         Construction of CISF campus and non-residential buildings in the campus of RGTPP at Khedar in Hisar district costing Rs. 18.24 crores – Progress : 22% achieved against 16%, Target date : 31.12.09

·         Construction of 48 nos type II, 96 nos  type III, 96 nos type IV (G+3 storey), 8 nos type VII (Duplex) and 1 nos type VIII (Duplex) houses in the campus of RGTPP at Khedar in Hisar district costing Rs. 26.00 crores – Progress : 4% achieved against 10%, Target date : 19.5.10 (The work was held up in some blocks as the road was passing through the site).

  1. Construction of high level bridge over Tangri River at RD 47.80 on Jagadhari Ambala road of 8 span of 18 mt each (app.) alongwith its approaches in Ambala district. (Amount Rs. 7.52 crores) – The work has since been completed.
  2. Construction of suspension cable foot Bridge on Ghaggar River crossing link road Khartia Barisher Road to Kharak in Panchkula Distt. (Amount Rs. 75.00 lacs) – Complted.
  3. Construction of ROB at Samalkha costing Rs. 21.24 crores – Financial Progress : 9.55%, Target date : September, 2010.  (Work held up due to approval of revised drawings from railway).
  4. Construction of ROB at Kosli costing Rs. 19.47 crores – Progress : 5.23% against 7%, Target date : February, 2010
  5. Const. of Icon buildings in Murthal Engineering College (Amount Rs. 56.40 crores) – Tenders has been invited and are to be received on 18.02.2009.
  6. 4-laning of roads in Rewari town and construction of new roads – (Amount  Rs. 131.75 crores). Work has been allotted on 30.1.09.
  7. Improvement of Hodal-Punhana-Nagina Road, improvement of roads from Palwal-Hathin road to Uttawar Sikrawa to Bhadas Road and improvement of BKP road upto GA road (Amount Rs. 183.12 crores). Work has been allotted on 30.1.09.
  8. Improvement of Jhajjar Dhaur Beri road, Dighal Beri Jahazgarh road and Bahadurgarh Chhara Dujana Beri Jahazgarh road in Jhajjar Distt (Amount Rs. 212.23 crores). Work has been allotted on 30.1.09.
  9. Upgradation of Chandimandir Jallah road in Panchkula district costing Rs. 30.00 crores. Tenders have been received on 30.1.09 & are under process.
  10. Upgradation of Deodhar to Nainawali road & links in Yamuna Nagar district costing Rs. 45.00 crores. Tenders have been received on 30.1.09 & are under process.
  11. Improvement by raising , widening, strengthening and providing side drains, CC pavement on various roads in Jhajjar District. Estimated Amount- Rs.153.54 Crore Financial bid opened on 23/02/2011 & under process
  12. Improvement by raising , widening, strengthening and providing side drains, CC pavement on various roads in Sonepat District. Estimated Amount- Rs.114.56 Crore Financial bid opened on 23/02/2011 & under process.
  13. Construction of Badli Byepass Km 0.000 to Km 5.681 and improvement of 2 Kms of existing Bahadurgarh Badli Chandu border road in NCR area in Jhajjar Distt. Financial bid opened on 25/03/2011 & under process.

 

 

 
© All rights reserverd to HSRDC